Estimated timeline for Betham Water Recycling Project

  • Period: to

    CPG-PUB and WASA consult on BWRP

    CPG consults with WASA on BWRPIn August 2012, CPG, in collaboration with PUB Consultants Pte Ltd, through an MOU signed between PUB and WASA, was commissioned by WASA to undertake a technical study and concept design for the Beetham Water Reuse Project. The objective was to study the feasibility and develop a technical concept design for a water recycling plant that will convert the treated effluent from BWWTP into high grade industrial process water for supply to industrial users. CPG and KPMG Singapore prepare RFP
  • WASA obtains a $246M USD IDB loan for wastewater works

    WASA obtains a $246M USD IDB loan for wastewater works
  • RFP for Beetham Water Recyling Project advertised

    RFP for Beetham Water Recyling Project advertised
    NOTICE OF TENDER for Design & Build, and Operation & Maintenance of the Beetham Water Recycling Plant published on 2 September 2013 by NGC
  • T&T Budget statement read in Parliament

    T&T Budget statement read in Parliament
    The budget statement is delivered by Minister of Finance & the Economy, Sen Larry Howai, with no mention of the Billion-Dollar BWRP, the RFP for which was published a mere seven days prior.
  • Desalcott plans expanding output

    Desalcott plans expanding output
    The Minister of the Environment & Water Resources, makes a formal statement detailing the expansion of Desalcott’s daily output from 32 million to 40 million gallons.
  • SISL gets $1B contract for BWRP

    SISL gets $1B contract for BWRP
    BWRP contract was awarded to SIS Ltd and its subcontractors in the sum of $1.043 Billion.
  • Desalcott expansion delayed

    Desalcott expansion delayed
    WASA announces that Desalcott’s expansion programme is delayed and will take effect in April, instead of January as originally anticipated.
    Statement from WASA