Production Schedule Updated

  • Recreate Storyboard

    Recreate Storyboard
    Lost storyboard needs to be recreated,
    Meet up in starbucks after equipment collection for holiday filming.
    - Day 1 Filming Failed moved to 1st Nov 2014
  • Period: to

    Filming Schedule

  • Filming Day 1

    Filming Day 1
    Meet up at Wapping Station and get the wapping archway tunnel shots, Then go to southwark to get bubble wrap lighting shots and artist singing and dancing in these locations. Nicole - Artist needed for all shots
  • Filming Day 1

    Filming Day 1
    Filming Projection shots during lesson on 7/11/2014
    In college room 333
    Project shot of gifs relating to the song at the back while singer in singing the song and moving around
    no props needed
    • Possible test shots, may need to reconsider redoing Nicole - Artist required for all shots.
  • Filming Day 2

    Filming Day 2
    Meet at wapping archway tunnel and film pillar shots and movement shots.
    Artist needed - Nicole
    Black costume with Boots Kings Cross Granary Square Fountains, Dancing on fountains singing, and dancing camera movement with the artist Semi dark natural light, artificial lights required.
  • Editing Day 1

    Look through all the footage gained.
    start placing on the timeline.
    start marking the beat.
    plan whether to refilm any footage.
    make a list of where to go from this point of the project.
  • Filming Day 3

    Film more projection shots.
    Gifs at the background with Nicole singing in front of the camera.
  • Period: to

    Editing Schedule

  • Filming Day 4

    Filming at Mulberry School For Girls Drama Studio at 3:30
    Filming all the shots that require a black room,
    Nicole - artist needed for all shots. Possible props:
    - Shisha Pen
    - Glass
    - Chair Costume:
    - Oversized White T-Shirt
    - Black Jeans
  • Filming Day 5

    Decided to dedicate the whole day to filming
    1st Location: Photography Studio in Bethnal Green 10am-2pm
    - Shots using white room, Replicate to an extent shots from black room.
    - Props: Glass, Shisha Pen, Cigarette, Chair
    - Costume: Black Outfit.
    2nd Location: Greenwich Foot Tunnel
    - Reshoot Tunnel shots, Walking down
    - costume: Black Outfit.
    3rd Location: Granary Square Fountains
    - Reshoot Fountain Scene due to bad lighting.
    4th Location: London Bridge southwark st
  • Filming/Editing

    Look Through all footage, Film more projection shots in first half of lesson if needed. or other shots that may be needed - Hopefully get it perfect the first time. Carry on Editing.
    Place all basetracks on timeline.
    Mark to the Beats and cut
  • Editing

    Work on Placement of footage so cut out the parts of the base track not wanted. keep looking over footage as we go along the process. refer back to storyboard.
  • ROUGH CUT

    Add in rough effects eg. black and white and slow motion ready for submission of rough cut
  • Editing

    work on rough cut feedback, Fix up video reflecting on footage, make any other changes that we want.
  • FINAL DEADLINE !!!!!!

    Check through all shots, finishing touching, MAKE SURE SOUND OF VIDEO IS OFF SO DOESN'T INTERFERE WITH SOUNDTRACK AND PROFESSIONALISM OF MUSIC VIDEO
    MAKE SURE THE MOUTH MOVEMENT OF THE ARTIST IS PERFECTLY SYNCED WITH THE SONG
    ENSURE EVERYONE IN THE GROUP IS HAPPY WITH THE FINISHED PRODUCT. LAST FEW TOUCHES.